Price adjustment calculator
Apply your contract’s adjustment formula: fixed part, coefficients and indices.
Indicative tool, to be checked against your contract: the contract and the applicable text prevail over this calculation.
Result
Fill in all the fields to get the result. The calculation runs in your browser: nothing is sent.
The formula
P = P0 × (a + b1 × I1 ÷ I01 + b2 × I2 ÷ I02 + …)
P0 is the initial price, a the fixed part, b the coefficients of the indexed parts, I the indices at the adjustment date and I0 the base indices. In a complete formula, a + b1 + b2 + … = 1. The coefficient is not rounded: apply any rounding your contract requires.
Where to find the parameters
This is the usual parametric form; your contract may set another. The contract terms define the formula, its coefficients, the indices to use, their reference month and the trigger conditions. Indices come from the official source they name.
Fictitious example
For a price of 1,000,000, a fixed part of 0.15 and one index rising from 100 to 110 with a coefficient of 0.85: 1,000,000 × (0.15 + 0.85 × 110 ÷ 100) = 1,085,000. These values illustrate the calculation.
Track these amounts contract by contract
Tendora calculates interest and penalties on your payment statements and milestones, from tender to close-out.
- 7-day free trial
- No credit card
- No commitment

